This is how a Lappli house is constructed

Lappli house is erected quickly: the average duration of the entire project is 6 months. The panelised wall system makes construction faster in the initial phase of the project, in particular; unfinished houses are soon protected against the weather. We will support you, as necessary, throughout the construction project.

 

The customer manages

The customer together with Lappli-HOUSES

Lappli-HOUSES manages

 

Choosing or designing the suitable house model, acquiring the plot and finding out the planning regulations

Lappli’s designers will help, as necessary

 

 

Determining the content of the delivery, selecting the suitable installation scope and time of delivery

 

Invitation to make an offer

 

Making and introducing the offer

 

Concluding the transaction

 

 

Preliminary approval of the house model by the building supervision,
 obtaining the main designer and the site foreman

Lappli will help, as necessary

 

Having the layout plan prepared, applying for a building permit, having the foundation plan prepared

 

Order acknowledgement from the factory to the customer

 

 

Preliminary scheduling of production

Inspecting and approving the order acknowledgement and main drawings

 

 

 

 

Ordering the building components from subcontractors, preliminary selection of the installation team, making the construction plan for the customer, making the foundation dimension drawing for the customer

Performing the earthwork and preparing the foundations/having them performed and prepared

 

Making the panselised wall system drawings for production, binding scheduling of production and transport

 

 

Delivering the house package and installing it up to the agreed phase

Inspecting, approving and documenting the installation work

 

 