This is how a Lappli house is constructed
Lappli house is erected quickly: the average duration of the entire project is 6 months. The panelised wall system makes construction faster in the initial phase of the project, in particular; unfinished houses are soon protected against the weather. We will support you, as necessary, throughout the construction project.
The customer manages |
The customer together with Lappli-HOUSES |
Lappli-HOUSES manages |
|
Choosing or designing the suitable house model, acquiring the plot and finding out the planning regulations |
Lappli’s designers will help, as necessary |
|
|
|
Determining the content of the delivery, selecting the suitable installation scope and time of delivery |
|
|
Invitation to make an offer |
|
Making and introducing the offer |
|
|
Concluding the transaction |
|
|
Preliminary approval of the house model by the building supervision, obtaining the main designer and the site foreman |
Lappli will help, as necessary |
|
|
Having the layout plan prepared, applying for a building permit, having the foundation plan prepared |
|
Order acknowledgement from the factory to the customer |
|
|
|
Preliminary scheduling of production |
|
Inspecting and approving the order acknowledgement and main drawings |
|
|
|
|
|
Ordering the building components from subcontractors, preliminary selection of the installation team, making the construction plan for the customer, making the foundation dimension drawing for the customer |
|
Performing the earthwork and preparing the foundations/having them performed and prepared |
|
Making the panselised wall system drawings for production, binding scheduling of production and transport |
|
|
|
Delivering the house package and installing it up to the agreed phase |
|
Inspecting, approving and documenting the installation work |
|
|